Keep the Good, Replace the Weak Link
Boiler feed regulating valves at a UK power station
Much critical plant is mechanically sound but let down by one unreliable component. Replacing the whole asset means pipework or civil work, long outages and high cost. Re-engineering only the weak link keeps the serviceable, fit-for-purpose equipment that would be costly and disruptive to replace.
At a large UK power station, IPT Engineering and Beck did exactly that on the boiler feed regulating valves. The upgrade was designed jointly by Beck and IPT, manufactured by Beck, and installed and commissioned with IPT’s support.